DEVELOPMENT SCHEDULE
16 months
DEVELOPMENT COST
$80 million
USE
Regional Ground Distribution Center
SPECIAL FEATURES
- Pile supported building required due to poor existing soil which consisted of municipal waste, asphalt millings, and processed dredge material
- Wetlands impacts
- Developed within 100-year floodplain area; Included importing fill to raise site elevation
- Mechanically pre-treating stormwater before discharging